News and Updates

US 1 Paving



Paving on US 1 is scheduled to begin on Sunday, July 29, 2018.  This work will take place nightly between 9 p.m. and 6 a.m. and will require one additional lane closure.  One travel lane will remain open in each direction at all times. 

_______________________________________________________________________________________________________

Tequesta Drive Railroad Grade Closure - FEC Project (not Village's)
August 18 - 21, 2018
Location:

  • Tequesta Drive and Old Dixie

Time:

  • Complete closure 

Type of Work:


The roadway grade crossing will be under
a full roadway closure for four days:

  • DAY 1 – (Begin 7:00 am) MOT detour put in place, Track Panel rehabilitation built off-line and demolition of existing crossing surface begins (saw-cutting of pavement, Panel removal, etc).
  • DAY 2 – Existing Roadway Surface Material removed, New Track panel completed, Existing panel removed, New Panel installed, with thermite welds, and Ballast placement, regulator and vibrating of newly installed panel.
  • DAY 3 – Alignment and vibrating of Ballast and grading/Alignment of Track, install Crossing surface Panels, Install Asphalt Base pavement for Panel stabilization and Roadway Pavement removed.
  • DAY 4 – (Ending 11:59 pm) Install Final Roadway pavement, complete Paint Striping, Clean Job Site, Remove Detour and open Roadway, Demobilize.
For information contact:

___________________________________________________________________________

Lighted Medians to Recognize Specific Causes

Our Public Works Department has started illuminating the median on Tequesta Drive near Cypress with colored lights in recognition of various causes. January the median was pink in support of "Breast Cancer Race for the Cure." February will be red in support of "American Heart Month." This is our small way of bringing attention to important causes and hopefully raise awareness. Click here for the full list of causes and colors that will illuminate the median throughout 2017. For more information, contact Public Works at 561-768-0482.