The Beach Road Water Main Replacement Project will replace 1960’s era water mains serving customers on Beach Road. These 60-year pipes have served the community well and are now at the end of their service life. The new piping has a service life of 50+ years and will help to ensure you continue to receive the safe, reliable and great tasting water you’ve come to expect.
Location: Location Map
Budget: $491,000
Funding Source: Water Enterprise Fund & Developer Contributions
Start Date: November 2019
Projected Finish Date: April 2021
Project Contact: David Tinoco 561-768-0484 dtinoco@tequesta.org
Current Status: Johnson-Davis has completed all water main installations and passed pressure testing. Bacteriological samples will be collected this week and the new water main put in service once cleared by the Palm Beach County Department of Health. (Updated 4/13/21)