Well Rehabilitation Project

The Utility Department is rehabilitating 3 of the 4 Floridan Aquifer Wells that feed the reverse osmosis process at the water treatment plant. Rehabilitating the wells ensures that they function at their peak capability for many years.

Budget: $416,979.03

Funding Source: Water Enterprise Fund

Start Date: December 2021

Projected Finish Date:  May 2022

Project Contact:  Nate Litteral 561-768-0493  nlitteral@tequesta.org

Current Status:  

The Village contracted with Florida Drilling in November 2021 to complete the work. Florida Drilling has set up the temporary piping needed for the project and started the rehabilitation process on Well No. 4. (Updated 1/5/22)