Country Club Drive North Water Main Replacement

The Country Club Drive North Water Main Replacement Project will replace 1950’s & 1960’s era water mains serving customers in the vicinity of Country Club Drive north of Eastwinds Circle. These 60 & 70-year old pipes have served the community well and are now at the end of their service life. The new piping has a service life of 50+ years and will help to ensure you continue to receive the safe, reliable and great tasting water you’ve come to expect.

Budget:    $1,174,000

Funding Source:    Water Enterprise Fund

Start Date:    November 2021

Projected Finish Date:    Summer 2023

Project Contact:     David Tinoco 561-768-0484  or email

Current Status:  

Design for the project has started and preliminary field activities including subsurface utility locates, survey and geotechnical investigations are underway (Updated 12/6/21)