2022 Road Improvement Project

The Road Improvement Project begins January 19, 2022 and runs through February 28, 2022.


  • Vehicles will be able to drive on the road after milling. 
  • Use caution when driving on milled roads as the roads will be uneven.
  • Roads will be closed during the paving process (refer to schedule below for closures).
  • ALL vehicles will need to be moved off the road until paving is complete. You will not be able to drive on the road during paving.
  • Any changes to the road improvement schedule will be posted on the Village Website.

Contact:  Public Works Dept. 561-768-0482

Milling Schedule:

DateArea
January 19, 2022                          Franklin Rd. between Venus Ave. and Seabrook Rd.
January 21, 2022Church Rd  between Venus Ave and Seabrook Rd. 
January 24, 2022Beacon St. Between Venus Ave and Seabrook Rd. 
January 25, 2022Dogwood Ridge
January 26, 2022Hemlock Ave.
January 26-28, 2022Hickory Hill Rd
January 31-February 1, 2022Pinetree Circle
February 2-3, 2022Ridgewood Circle
February 4, 2022Willow Road


Paving Schedule:

DateArea
January 24, 2022  (Road Closed)     Franklin Rd. between Venus Ave. and Seabrook Rd. 
January 25, 2022  (Road Closed)     Church Rd  between Venus Ave and Seabrook Rd.
January 26, 2022  (Road Closed)     Beacon St. Between Venus Ave and Seabrook Rd. 
Dogwood Ridge                            TBD (To be Determined)
Hemlock Ave.                              TBD 
Hickory Hill Rd                             TBD 
Pinetree Circle                              TBD 
Ridgewood Circle                          TBD 
Willow Road                                TBD 
Milling and Resurfacing Map