Country Club Community Capital Improvement Project Update:
- The Project is in its 8th week. The new stormwater catch basins have been installed on El Portal Drive.
- Installation of a NEW sidewalk is underway on the South Side of El Portal Drive.
- Weather permitting the sidewalk will be completed by 11-17-23.
- Grading the swales, irrigation repairs and edge of road repairs, will begin 11-13-23 and run through 11-30-23.